Project Budgets and Timelines

This list shows the approximate budget and dates of the design or construction phase of De Anza's Measure E projects.

Projects In Design
Project Name Design Construction Current Budget

None

   
[top of page]
Projects In Construction
Project Name Design Construction Current Budget
Visual & Performance Arts Center 2003-06 2007-08
12,500,000
[top of page]
Projects Completed
Project Name Design Construction Current Budget
A & B Stelling Entry 2002-03 2004
2,359,000
A & B Landscape 2002-03 2004
270,000
A Quad (Phase I) A5 & A7 2000 2003
986,000
A Quad (Phase 2) A1,2,3,4,6 2002-03 2004-05
2,605,000
A Quad (Phase 3) A8 & A9 2005-06 2006
1,750,000
Administration 2004-05 2005-06
3,600,000
Athletics Fields & Tennis Courts 2002-05 2005
3,146,000
Campus Center 2005-06 2006-07
5,100,000
Campus Entries 2004-06 2006-07
2,100,000
Californian History Center 2005-06 2006
545,000
CC-Fire Sprinkler Replacement 2002 2003
98,000
Child Development Center 2001 2003
5,575,000
Child Development Center Landscape 2003 2003
309,000
Child Development Center Wing B Renovation 2002 2003
604,000
E2-Machine Tech 2001 2002
650,000
Faculty Offices Renovation 2000 2002
1,581,000
Fire Alarm Panel Replacement 2001-03 2003-04
287,000
Irrigation Mainline 2004-05 2005
650,000
Fire Line Cross Connect 2004 2005
208,000
Kirsch Center 2002-04 2004-05
11,327,000
L Quad Renovations 2000-02 2002-03
4,351,000
Mobile Village 2002 2003
1,975,000
Parking Deck 2002-03 2003-04
12,718,000
PE Quad 2002-04 2004-05
9,293,000
Planetarium 2003-06 2006-07
1,200,000
Pool Renovation 2001 2003
1,657,000
Restrooms 2004-05 2005-06
580,000
S Quad, E3 2003-05 2005-06
9,917,000
S2/S6 Cooling Tower 2003-04 2005
677,000
Student and Community Services 2001-03 2005
14,627,000
Science Center 2000-02 2002-04
21,111,000
Utility Vault Replacement 2003 2004
190,000
Water Line Valve Replacement 2002 2003
796,000
[top of page]
Future Projects - Deferred to Measure C
Project Name Design Construction Current Budget
Campus Site Lighting TBD TBD
TBD
Forum TBD TBD
TBD
Master Landscape TBD TBD
TBD
Signage TBD TBD
TBD