Update on Measure E: Winter Quarter 2006

This quarter we will be continuing renovations to the S Quad, the Administration Building, and starting the renovation of the Californian History Center.

Projects Completed Through December 2005

  • A Quad (Phase I) A5 & A7 Renovation: Completed fall quarter 2002. This was a $1.2 million project.
  • A Quad (Phase II) all except A5, A7, A8 & A9: The was a $2.5 million project.
  • Athletics Fields & Tennis Courts: These areas were completed during summer 2005. The budget was $3 million
  • Boilers: Completed in June 2002.
  • Child Development Center (Landscaping): Phase I & II. Phase I was completed in September 2003 and phase II was completed in January 2005.
  • Child Development Center (New Addition): Completed in the summer of 2002. It was a 11,500 sq.ft. $5 million project.
  • Child Development Center (Renovation of Old Building – Wing A): This was the first phase of the two-phase renovation of the old Child Development Center building. Renovations were completed in winter 2003.
  • Child Development Center (Renovation of Old Building – Wing B): This was phase II of the renovation of the old Child Development Center building. Renovations were completed in July 2003.
  • Child Development Center – New playground funded by the Packard Foundation
  • E2: Completed fall quarter 2002 at a cost of $820,000.
  • Faculty Office Renovation Project: Completed in the spring of 2002. It was a $1.5 million project.
  • Kirsch Center for Environmental Studies: The Kirsch Center was on-line in fall quarter 2005. This was an $11 million project.
  • L Quad - L1, L2, L3, L4, L5, L6, L8 and MCC Renovation: These were all complete by July 2003 at a cost of $4.3 million.
  • Lot A & B Landscape: The landscape in this area was planted over the winter 2004 at a cost of $270,000.
  • OTI Relocation: The OTI staff moved to their new site in summer 2002.
  • Parking Lot A & B Reconfiguration and Stelling Campus Entry: This project was carried out in the summer of 2003 and completed in time for fall quarter 2003. It was a$2.3 million project.
  • Parking Structure: The lower section of the parking structure opened in fall quarter 2004, with the whole structure opened winter quarter 2005. Construction commenced in December 2003 and was completed at a cost of $12.8 million.
  • PE Quad Renovations: Work was completed in this area during summer 2005. The total budget was $9 million
  • Pool Renovation: Work was completed in March 2003. This was a $1.6 million project
  • S1 – S8 Cross Connect: This project was completed in spring 2005.
  • Science Center: The Science Center was on-line for fall quarter 2004. This was a $21 million project, which took 23 months of construction to complete.
  • Student and Community Services Center: The Student and Community Services Center was on-line in summer 2005. This was a $15 million project.
  • Tree Relocation: Two oak trees relocated in September 2002.

Projects Under Construction

Administration Building: The renovation includes the addition of four new multimedia classrooms. Substantial completion of work is scheduled for September 2006. The hazardous materials abatement work is complete and framing of the new walls and HVAC work is underway. The renovated building will house The President, Vice Presidents, Academic Services, Budget and Personnel, College Services, Diversity Office, Facilities Coordinator, Faculty & Staff Mailboxes, Institutional Research and Marketing. It will also include two conference rooms the Emergency Operations Center and three large multimedia classrooms. This is a $3.6 million project.

Future Classrooms Future Classroom

Demo of counseling and A&R areas which will become classrooms

Future Classroom Marketing

Framing for new classrooms and offices

 

Athletic Fields Barrier Netting: This project includes three netting barriers. Two barriers are between the baseball/softball fields and the Kirsch Center and the third is between the tennis courts and the fields. The College is working with the Physical Education division to schedule this project to minimize the impact on classes.

Californian History Center: Work has commenced with the prepping of the exterior of the building for repainting. Preparation work is also underway for the repair of the balustrades surrounding the Califiornia History Center and at the west and east ends of the sunken garden. This project will be complete by April 2006.

Preparation work on exterior

 

Restrooms: Renovation work will run from October 2005 through April 2006 at a cost of $580,000. Phase 1 of renovations to S6 and L5 is complete. Phase II, consisting of S2 and the Athletic Field restrooms, is currently scheduled for February through April 2006.

S Quad: This is an extensive $10 million, multi-phase, renovation project. Work is complete on Phase 1, comprising of S1, S4 & S8. Renovations to S3 should be complete by late February – mid March 2006. Once complete the Physical Science, Math & Engineering Division office will move back to S3. Phase II of this project is S5, S7 and E3. S7 is already complete and work on S5 and E3 is underway. Both S5 and E3 are scheduled for completion this summer.

Projects in Design

A Quad:

A9: Bid and award should be complete by mid March 2006 with construction scheduled for completion by beginning of fall quarter 2006.

A8: is in the final design phase with bid and award scheduled for April through end May 2006. Construction is scheduled for summer through October 2006.

Campus Center: The construction drawings are complete and are under DSA review. Construction is expected to start in late summer 2006 and run through summer 2007. Plans include an expanded dining service area as well as mechanical upgrades. The project budget is $5.9 million and primarily funded by the student body through the Campus Center Use Fee. During the renovation of the campus center, a reduced level of food services and cafeteria seating will be available in the upper level of the old bookstore.

Campus Entries: The goal of the project is to improve traffic flow on and off campus as well as on-campus circulation. The final Environmental Impact Report (EIR), incorporating the proposed removal of the east cottage, is complete and the final stage of the public review will take place at the March 6, 2006 Board meeting. Other design features included in this project are signage, landscaping, a new service roadway, new city sidewalks, and enhanced pedestrian lighting. Currently, the bid and award phase will commence in March 2006. This is a $2.1 million project.

Campus Site Lighting: We are currently in the design phase of this project. Bid and award is scheduled for April through June 2006. Work should take place through summer 2006. The project budget is $660,000.

Forum: Construction drawings are complete. DSA review and approval should be finalized by summer 2006. Renovations will follow the completion of the Administration building remodel. This is a $1.9 million project.

Performance Hall: The completion of the design phase is due to be finalized by fall 2006. Procurement is scheduled for early 2007. Construction of this new building is currently scheduled for summer 2007 through summer 2008. As this project is located on the present site of the Mod Quad, the demobilization of the MQ buildings will be the first step of the construction process. Proposition 55 which passed in 2004 will augment the Measure E dollars allocated for this project. There have also been external fund raising efforts to assist with the funding of this project. The current budget is $12.5 million.

Planetarium: Procurement is underway with renovations anticipated to take place spring through end of fall quarter 2006. The $1 million Star projector will be installed in fall quarter. This is a $1.2 million project (excluding the Star projector).

Future Projects

E1: a conceptual estimate based on site-walks with the end-users and district representatives is complete. The E1 renovation project is budgeted at $2.1 million.

ADA/Signage: $1.5 million.

We truly appreciate the cooperation we have seen from everyone and appreciate your continued patience as we continue our Measure E efforts.

Budget figures and timelines are approximations and are subject to change